Mining returns to the Yukon

Advanced projects prepare to follow Victoria Gold into production

by Greg Klein

Advanced projects prepare to follow Victoria Gold into production

Rich geology trumps challenging geography in Yukon’s appeal to miners.
(Photo: Victoria Gold)

 

If John McConnell seemed a tad tipsy it might have been due to giddiness, not the super-sized wine goblet he brandished. Either way, celebration was in order as the president/CEO of Victoria Gold TSXV:VIT took the podium at the Denver Gold Show this week to preside over a ceremonial first doré bar at Yukon’s new Eagle operation. The event marked not only the resumption of mining in one of the world’s most fabled mining regions, but the beginning of Yukon’s largest-ever gold mine. Meanwhile other companies vie to expand the industry’s territorial presence.

The festivities took place one month ahead of schedule and within a revised budget intended to address a capex miscalculation that marked one of the low points during what McConnell called a decade of ups and downs. Expected to produce an average 200,000 gold ounces annually for 10 years, Eagle currently employs about 230 people, half of them Yukoners.

Advanced projects prepare to follow Victoria Gold into production

Minto’s suspension left Yukon without a mine for
nearly a year, but a new owner plans a Q4 restart.
(Photo: Pembridge Resources)

The territory lost its last mining operation in October, but a new owner plans to bring that one back to production by Q4 this year. Capstone Mining TSX:CS put Minto on care and maintenance as acquisition negotiations faltered, but LSE-listed Pembridge Resources closed the purchase in June. Proven and probable reserves totalling 40,000 tonnes copper, 420,000 ounces silver and 45,000 ounces gold give Minto an estimated four more years of production.

Pembridge hopes to extend that, however, noting that “Minto had successfully replaced and grown reserves by 103%, adding new discoveries each year up until 2013.” That’s when Capstone suspended Minto exploration, after buying the much larger Pinto Valley copper mine in Arizona from BHP Billiton NYSE:BHP.

The central Yukon combined open pit/underground mine began operation in 2007. Pembridge wants its new cornerstone asset to achieve annual production of about 40 million pounds copper in concentrate, along with silver-gold byproducts.

Waiting in the wings with a project comparable to Eagle, Newmont Goldcorp’s (TSX:NGT) Coffee now has a territorial environmental/socio-economic review underway. Like Eagle, this would be an open pit, heap leach operation. The 2016 feasibility study by previous operator Kaminak Gold projected 10 years of mining, averaging 202,000 gold ounces annually based on a probable reserve of 2.16 million ounces. But last year, following Goldcorp’s 2016 acquisition of Kaminak, the new owner slashed that number to 1.67 million ounces.

Goldcorp cited different standards for drill spacing, geological modelling and other criteria but expected to rebuild the reserve with an 80,000-metre infill drill program scheduled for this year. More recently, however, the merged Newmont Goldcorp has talked about divesting some assets, casting uncertainty over Coffee’s near-term agenda.

But by far the territory’s biggest proposed mine would be Western Copper and Gold’s (TSX:WRN) Casino, in west-central Yukon. A 2013 feasibility report foresaw a combined heap leach and milling operation with 22 years of annual output averaging 171 million pounds copper, 266,000 ounces gold, 1.43 million ounces silver and 15.5 million pounds molybdenum.

Advanced projects prepare to follow Victoria Gold into production

Even with a recent feasibility in hand, BMC Minerals
wants to build its Kudz Ze Kayah polymetallic reserve.
(Photo: BMC Minerals)

Although the report boldly envisioned construction beginning in 2016 and commercial production in 2020, the company currently has environmental and engineering studies underway prior to submitting an application for an environmental/socio-economic review. Capex was estimated at $2.456 billion.

Meanwhile Western has two rigs drilling a $3.3-million, 10,000-metre program, with a resource update planned for this year and, coming later, a revised feasibility that the company hopes will extend the mine life.

Operating under the stock market’s radar, privately held BMC Minerals brought its Kudz Ze Kayah polymetallic project in south-central Yukon to full feasibility last July. The report sees a $587-million capex and 20-month construction period for a combined open pit and underground operation producing an annual average of 235 million pounds zinc, 32 million pounds copper, 56 million pounds lead, 7.8 million ounces silver and 56,500 ounces gold.

BMC hopes to lengthen the nine-year mine life by adding reserves and exploring new targets beyond the two zones considered in the feasibility study.

Sharing with Coffee a White Gold district address and a progenitor in legendary prospector Shawn Ryan, White Gold TSXV:WGO holds 35 properties covering some 439,000 hectares. Last June the company released resource updates for its two most advanced deposits. Golden Saddle hosts an open pit resource of 1.01 million gold ounces indicated and 259,600 ounces inferred, along with an underground resource of 12,200 ounces indicated and 54,700 ounces inferred. The Arc deposit adds an open pit resource of 17,700 ounces indicated and 194,500 ounces inferred.

With money from Agnico Eagle Mines TSX:AEM and Kinross Gold TSX:K, each holding 19% of White Gold, the company has a $13-million drilling, trenching and sampling campaign now targeting Golden Saddle and the new Vertigo discovery, along with other areas. Among noteworthy intercepts was 3.59 g/t gold over 68 metres starting from 73 metres at Golden Saddle. Using a method integral to Ryan’s successes, soil sampling surpassed 100,000 ppb gold at the new Titan discovery, the highest value on the company’s database of over 400,000 soil samples.

Taking advantage of a past producer with all permits in place, Golden Predator Mining TSXV:GPY last month stated it began site re-development work and “provided formal notice to the Yukon government to move the Brewery Creek mine into the production phase.” The company has also stated it plans a feasibility study before making a production decision. Located about 55 kilometres east of Dawson City, the open pit and heap leach operation produced about 279,000 gold ounces between 1996 and 2002. The company plans at least 6,000 metres of drilling this year to build on a 2014 PEA.